Florida Seawall Permits · Tampa Bay

Pinellas County Seawall Permits: Water and Navigation and City Rules

Pinellas County runs one marine permit office for every shoreline in the county, cities included, and cities layer their own building rules on top. Here is how the pieces fit, from the county permit to city height rules and state review.

Last reviewed November 2, 2026 Prepared by the Florida Bulk Head editorial team 17 cited sources
Quick answer

Who issues seawall permits in Pinellas County?

Pinellas County's Water and Navigation section permits seawalls, riprap and docks in all 24 cities and unincorporated areas, through the Pinellas County Access Portal. A separate building permit is often needed too: the county requires one for seawalls of any height in unincorporated areas, and some cities publish their own seawall checklists. State review generally goes to the DEP Southwest District or SWFWMD, and the Corps handles federal authorization.

Not legal or permitting advice

Permit requirements depend on your exact property, the waterway, the work proposed and every agency with jurisdiction. This guide points you to official sources; confirm requirements with each agency before starting work.

Agencies that may be involved

LevelAgencyTypical role
FederalU.S. Army Corps of Engineers, Jacksonville District Federal authorization for structures in navigable waters and fill in waters of the United States
StateFlorida DEP Southwest District State ERP exemptions and permits for single-family work not part of a larger development, usually with state-lands review; the district includes the Pinellas County and Boca Ciega Bay aquatic preserves
StateFlorida DEP Coastal Construction Control Line Program Permits for construction seaward of the CCCL on Pinellas County's Gulf beaches
RegionalSouthwest Florida Water Management District ERP review for projects DEP does not handle, such as work within a larger permitted development
CountyPinellas County Public Works, Water and Navigation section Permits for seawalls, riprap, docks, tie poles and all dredging or filling in county waters, in the cities and unincorporated areas
CountyPinellas County Building and Development Review Services Building permits and inspections for unincorporated Pinellas County and six cities it serves as building department (the county calls them partner communities); seawalls of any height need a building permit in unincorporated areas
MunicipalCity of St. Petersburg Construction Services and Permitting Division Building permits and inspections inside St. Petersburg city limits
MunicipalCity of St. Pete Beach Building Department Seawall permits under the city's Seawall Permitting Requirements, including minimum seawall elevations
MunicipalCity of Madeira Beach Building Department Seawall permits under the city's seawall checklist, which limits how high a new cap may go
MunicipalCity of Clearwater Planning and Development Department Pre-approval required before a Clearwater dock application goes to the county Water and Navigation section

Who Issues What in Pinellas County

Pinellas County's Water and Navigation section (opens in a new tab) permits docks and 'dredge and fill' projects, and the county states plainly that 'this includes projects in the cities and unincorporated areas.' Seawalls and riprap are on its list, along with private, multi-use and commercial docks, marinas, tie poles and 'all dredging or filling within the waters of Pinellas County.' The county has 24 incorporated municipalities, and the same county marine permit applies in each of them.

The building permit is a separate track. In unincorporated Pinellas, the county's Fences & Walls page lists 'seawalls of any height' among work that always requires a building permit, and Seawall is a residential permit type under Fences and Walls. Building and Development Review Services also acts as the building department for six cities, which the county calls partner communities (not to be confused with Florida Bulk Head's contractor network); Indian Rocks Beach, for example, says the county has assumed the role of its building department. Other cities, including St. Petersburg, St. Pete Beach and Madeira Beach, run their own building offices.

Where a typical Pinellas County seawall project goes (confirm with each office)
Where the property isCounty marine permitBuilding or city permitAlso check
Unincorporated PinellasWater and Navigation, through the Access PortalCounty building permit (seawalls of any height)DEP Southwest District or SWFWMD; Corps
St. PetersburgWater and NavigationAsk the city's Construction Services and Permitting Division which permit appliesAquatic preserve limits in Boca Ciega Bay, southwestern Tampa Bay and Riviera Bay
St. Pete BeachWater and NavigationCity seawall permit with minimum elevations (5.0 ft bay, 6.0 ft Gulf, NAVD 88)CCCL permit for Gulf-front work seaward of the line
Madeira BeachWater and NavigationCity seawall checklist with a maximum cap heightDrainage and erosion control plans
Indian Rocks BeachWater and Navigation; the city's guidelines say seawalls need no city approval firstPinellas County Building Services acts as the city's building departmentCCCL permit for Gulf-front work seaward of the line
ClearwaterWater and Navigation; dock work needs city pre-approval firstAsk the city about seawall review; boat lifts need a building permitAquatic preserve limits in Clearwater Harbor

The County Water and Navigation Permit

Water and Navigation reviews projects 'for environmental impacts, navigational impacts and construction requirements, as well as consistency with the Pinellas County Water and Navigation Code.' New applications go through the Pinellas County Access Portal (opens in a new tab), where the county's instructions say to choose the Dock/Dredge & Fill Permit record type. A paper application is available by request at (727) 464-4170 or WNPermitIntake@pinellas.gov. For status on a filed application, email WaterNavPermits@pinellas.gov with the permit number and address.

  • Check habitat first. The county's Coastal Environmental Resource Zone Map (opens in a new tab) shows whether a property falls in a zone where 'seagrass and/or mangroves have been found nearby' based on the county's most recent data.
  • Watch review times. The county publishes a Water & Navigation Permit Times Dashboard (opens in a new tab) with permits issued, first review times and what is on schedule or delayed.
  • Know the fee structure. The county's fee schedule (opens in a new tab) (effective Oct. 1, 2026) lists dock permit types and dredge/fill permit types priced by volume, but no line item named for seawalls, so ask staff which type your wall falls under. The schedule also lists pre-application coral and mangrove surveys.
  • Mangroves. DEP lists an Order of Delegation to Pinellas County for the regulation of mangroves (02/27/96), and the county's fee schedule includes mangrove trimming permits.
  • Old pilings have disposal rules. The county says CCA-treated lumber must go to a permitted landfill, by appointment, cut to 4 feet or less and free of wires, metal attachments and decking.

Do not start before the permit

The county's fee schedule charges after-the-fact applications for unauthorized but permissible work at multiples of the normal or revision fee, up to five times, plus any fines. Its hurricane recovery page also reminds owners that repairing or replacing a dock, seawall, marina, riprap or tie poles may need a permit.

City Seawall Rules: Height Limits Run Both Ways

Two Pinellas barrier-island cities publish seawall height rules, and they pull in opposite directions. St. Pete Beach sets a floor; Madeira Beach sets a ceiling tied to the street and the neighbors. Neither rule applies outside that city, so check your own city's requirements before design.

Published seawall elevation rules in two Pinellas cities
CityWhat the city document saysWhat it asks you to submit
St. Pete Beach (Seawall Permitting Requirements, effective May 25, 2021)'All seawalls must be elevated to at least 5.0 FT (NAVD 88) on the bay side and at least 6.0 FT (NAVD 88) on the Gulf side.' If a wall cannot reach that, a signed, notarized and recorded Seawall Agreement is required, and the plans must show the wall can be raised later.Permit application, copy of contract, ground floor elevations of the house and both neighbors, two sets of sealed plans showing the new cap elevation, and a final elevation certificate before final inspection
Madeira Beach (Building Department seawall checklist)'Seawall cap cannot exceed elevation of the center line of the road and/or one (1) foot above neighbor's seawall cap.'Signed and sealed drawings (with a profile drawing if raising the cap), a current sealed boundary and topographic survey, an erosion control plan, and a drainage plan if raising the cap
  • St. Pete Beach turbidity barrier. A city notice to seawall contractors says a turbidity barrier must be installed before any construction, and failure to do so 'will result in a failed inspection and stop work order.' The 2021 sheet is the document we confirmed; ask the city whether a later standard applies. Our St. Pete Beach page has more.
  • Madeira Beach applications are submitted through the MGO Connect portal listed on the checklist; the Building Department is at 300 Municipal Drive.
  • Indian Rocks Beach. The city's posted guidelines list seawalls and dredge and fill among permits that go to Pinellas Water & Navigation without city approval, while docks need city approval first.
  • Clearwater. The city's Marine and Dock Permit Checklist (opens in a new tab) says its Planning and Development Department 'must provide pre-approval' before a dock application goes to the county, and that boat lifts require a building permit. It does not address seawalls, so ask the city before a combined seawall and dock job.
  • St. Petersburg. The Construction Services and Permitting Division (opens in a new tab) handles building permits at the Municipal Services Center. We did not confirm which city permit type applies to a private seawall; see our St. Petersburg page for the city's seawall planning.
  • Other cities. For Treasure Island, Gulfport, Dunedin, Tarpon Springs and the county's other municipalities, ask the city building office what it requires alongside the county permit.

Aquatic Preserves and the Pinellas Bulkhead Line

The Pinellas County Aquatic Preserve (opens in a new tab) 'includes all the state-owned submerged land within the boundary of Pinellas County,' extending 9 miles into the Gulf and following the county line in Tampa Bay. It also reaches fresh water, taking in large portions of Lake Tarpon and Lake Seminole. Its estuarine basins include the Anclote River, St. Joseph Sound, Clearwater Harbor, Boca Ciega Bay, southwestern Tampa Bay, Riviera Bay, Feather Sound and western Old Tampa Bay.

Inside it sits the Boca Ciega Bay Aquatic Preserve (opens in a new tab), which DEP describes as the first legislatively designated aquatic preserve in Florida, established in 1969 'in response to extensive dredge-and-fill activities.' Both preserves are managed under one DEP management plan, and a draft of a new plan was posted in 2026.

  • No new walls waterward of the high water line. Rule 18-20.004(1)(c), F.A.C. (opens in a new tab) says there shall be no construction of seawalls waterward of the mean or ordinary high water line in aquatic preserves, except for certain public road and bridge projects and as provided in section 258.42(3)(e)4., F.S.
  • Restoration allowance. Section 258.42(3)(e)4., F.S. (opens in a new tab) allows restoration of seawalls at their previous location, upland of it, or within 18 inches waterward, while Rule 18-20.004(1)(e)7. still uses one foot for restoration exempt from a consent application. Confirm the allowance with DEP before design.
  • The Pinellas bulkhead line. Statewide, section 253.1221, F.S. (opens in a new tab) re-established old bulkhead lines at the line of mean or ordinary high water. Pinellas has its own provision: under section 253.66, F.S. (opens in a new tab), once a county bulkhead line fixed by 'the water and navigation control authority of Pinellas County' is approved by the state's Board of Trustees, 'no further change in said bulkhead line shall be made.' A bulkhead line is not a property line or a permit; ask Water and Navigation whether one affects your shoreline.
  • Estuary walls may need riprap. For repair or replacement of an existing vertical seawall, section 373.414(5), F.S. (opens in a new tab) says the agency 'shall generally require such seawall to be faced with riprap material, or to be replaced entirely with riprap material' unless an exception applies, such as an existing manmade canal already lined with vertical seawalls. DEP describes Tampa Bay as Florida's largest open-water estuary.
  • Gulf beaches. Pinellas County's Coastal Construction Control Line is described in Rule 62B-26.011, F.A.C. (opens in a new tab). It covers the sandy Gulf beach and dune system, not bay, canal or lake walls.
  • Manatees. FWC's list of approved county manatee protection plans does not include Pinellas County as of this review. Ask DEP which in-water work conditions apply to your project.

State and Federal Review

Pinellas lies in DEP's Southwest District and in the Southwest Florida Water Management District. Under the DEP and water management district operating agreements (opens in a new tab), DEP generally reviews systems serving a single-family home that are not part of a larger development, plus anything seaward of the CCCL; SWFWMD takes the other ERP applications. State-owned submerged land in Pinellas is aquatic preserve, so state-lands authorization usually rides along with that review.

For federal authorization, the Corps' SPGP VI lists an expiration date of July 27, 2026, and we could not confirm a successor as of this review. Federal authorization may instead come through a nationwide permit, such as NWP 3 (Maintenance) or NWP 13 (Bank Stabilization), under the 2026 reissuance (opens in a new tab) that took effect March 15, 2026, or through an individual permit. Ask DEP or the Corps which applies to your project.

Typical Permit Steps in Pinellas County

  1. Confirm your jurisdictionFind out whether the property is in a city or unincorporated Pinellas, since that decides who issues the building permit. The county permit applies either way.
  2. Check habitat and city rulesLook up the Coastal Environmental Resource Zone Map, and read your city's seawall checklist, including any minimum or maximum cap elevation.
  3. Define the scopeHave the wall assessed and decide between repair and replacement. Note where the new face would sit relative to the old one, since aquatic preserve and state exemption limits turn on that distance.
  4. Get city pre-approval if requiredSome cities review first; Clearwater, for example, requires pre-approval before a dock application goes to the county.
  5. Apply to Water and NavigationSubmit through the Pinellas County Access Portal with the drawings and surveys the county asks for.
  6. Handle state, federal and building permitsConfirm the DEP exemption, self-certification or ERP, the federal authorization, and the city or county building permit, plus a CCCL permit for Gulf-front work.
  7. Build and close outInstall turbidity controls before work, pass inspections, file any required elevation certificate and dispose of old treated pilings properly.

Service in Pinellas County

Pinellas County is outside Barefoot Marine Construction's direct service area. Florida Bulk Head accepts inquiries here through a partner network that is still being built; matching is subject to contractor availability.

Documents and Contacts

Commonly requested for a Pinellas County seawall project

  • Water and Navigation application through the Access Portal (Dock/Dredge & Fill Permit)
  • Building plans signed and sealed by an architect or engineer for structural work, as the county's residential permit page requires
  • Current sealed boundary and topographic survey (Madeira Beach) or neighbor and floor elevations (St. Pete Beach)
  • Profile drawing and drainage plan if the cap is being raised
  • Erosion control or turbidity barrier plan
  • City pre-approval where the city requires it before the county application
  • DEP exemption verification, self-certification or ERP, and federal authorization
  • Recorded Seawall Agreement in St. Pete Beach if the wall cannot meet the minimum elevation

Frequently asked questions

I live inside a Pinellas city. Do I still need a county permit for my seawall?

In most cases, yes. Pinellas County's Water and Navigation section permits seawalls, riprap and docks in the cities as well as unincorporated areas. Your city may also require its own building permit or review, so ask both offices before work starts.

Does a seawall in unincorporated Pinellas need a building permit?

Yes. The county's Fences & Walls page lists seawalls of any height among work that always requires a building permit, and Seawall is a residential permit type in the Access Portal. That is in addition to the Water and Navigation permit.

How high does my Pinellas seawall have to be?

It depends on the city. St. Pete Beach's 2021 requirements set minimums of 5.0 feet NAVD 88 on the bay side and 6.0 feet on the Gulf side, while Madeira Beach's checklist caps a new wall at the road centerline elevation and/or one foot above the neighbor's cap. We did not find a countywide seawall height standard, so check with your city.

Is my seawall in an aquatic preserve?

If the wall fronts state-owned submerged land, probably. The Pinellas County Aquatic Preserve includes all state-owned submerged land in the county, including large portions of Lake Tarpon and Lake Seminole. Some canal bottoms may be privately owned, so ask DEP whether state lands are involved.

What is the Pinellas County bulkhead line?

Section 253.66, F.S., provides that once a county bulkhead line fixed by Pinellas County's water and navigation control authority is approved by the state Board of Trustees, it cannot be changed. A bulkhead line limits filling; it is not a property line or a permit. Ask Water and Navigation whether one applies to your property.

What happens if seawall work starts without a permit?

The county's Water and Navigation fee schedule charges after-the-fact applications at multiples of the normal or revision fee, up to five times, plus any fines. Cities can add their own consequences; St. Pete Beach warns that work without a turbidity barrier gets a failed inspection and a stop work order.

Sources and references

  1. Docks / Dredge & Fill (Water and Navigation) — Pinellas County. Accessed November 2, 2026.
  2. Water and Navigation and Mangrove Trimming Permit Application Fees (effective Oct. 1, 2026) — Pinellas County. Accessed November 3, 2026.
  3. Fences & Walls — Pinellas County Building and Development Review Services. Accessed November 3, 2026.
  4. Residential Permits — Pinellas County Building and Development Review Services. Accessed November 2, 2026.
  5. Municipalities and Cities — Pinellas County. Accessed November 3, 2026.
  6. Pinellas County Permits (hurricane recovery) — Pinellas County. Accessed November 2, 2026.
  7. Seawall Permitting Requirements (effective May 25, 2021) — City of St. Pete Beach. Accessed November 2, 2026.
  8. Permit Checklist Seawall — City of Madeira Beach Building Department. Accessed November 3, 2026.
  9. Permitting Guidelines, Building Department — City of Indian Rocks Beach. Accessed November 3, 2026.
  10. Marine and Dock Permit Checklist — City of Clearwater. Accessed November 3, 2026.
  11. Southwest District — Florida DEP. Accessed November 2, 2026.
  12. Pinellas County Aquatic Preserve — Florida DEP Office of Resilience and Coastal Protection. Accessed November 2, 2026.
  13. Boca Ciega Bay Aquatic Preserve — Florida DEP Office of Resilience and Coastal Protection. Accessed November 2, 2026.
  14. Section 253.66, F.S., Change in bulkhead lines, Pinellas County — Florida Legislature. Accessed November 2, 2026.
  15. Operating Agreements (Pinellas County mangrove delegation) — Florida DEP Office of General Counsel. Accessed November 2, 2026.
  16. Manatee Protection Plans — Florida Fish and Wildlife Conservation Commission. Accessed November 2, 2026.
  17. SPGP VI permit (SAJ-2015-2575) — U.S. Army Corps of Engineers, Jacksonville District (hosted by Florida DEP). Accessed November 2, 2026. Lists an expiration date of July 27, 2026

Regulations, programs and conditions change. Always confirm requirements with the agency that has jurisdiction over your property.